Conference Proceedings
13th Australian Tunnelling Conference
Conference Proceedings
13th Australian Tunnelling Conference
Big Diameter Tunnelling Beneath Low Rock Cover
The North-South Bypass Tunnel is the first project to get underway as part of Brisbane's transport plan, which aims to improve the urban road network. The total length to be excavated is 6.8 km, which includes 4.8 km of driven tunnel and associated road connections._x000D_
Construction commenced in August 2006 with project completion targeted well before the contractual completion date of October 2010._x000D_
Due to the local geology, in particular the hard Brisbane tuff and neranleigh-fernvale formation, a combination of tunnel excavation methods are used. The majority of the tunnel is excavated by two tunnel boring machines which have a rate of progress of 16 - 20 m per day in rock having a compressive strength of between 80 and 150 MPa. Ten roadheaders operate at a rate of up to 2 m per day excavating the remaining tunnels, such as ramps, access tunnels, cross passages and merges._x000D_
The tunnel team are managing the challenges and complexities associated with tunnelling through the hard Brisbane rock. A major challenge arose during the planning of the initial mainline excavation underneath the Royal National Association Showground in Bowen Hills. This section contains low rock cover and historical maps indicate that the showground is located within a former topographic depression (alluvial valley), which a creek once flowed through.Due to traffic merge design requirements, both tunnel boring machine (TBM) and roadheader excavation methods were required to be used in this challenging geological profile. The answer was to stabilise the alluvium above both TBM section tunnels from the surface prior to excavation and to operate the TBM in single shield mode with immediate grouting of annular void from the tail shield. In addition, the roadheader section of tunnel required additional support by spiles and canopy tubes installed from the tunnel face.
Construction commenced in August 2006 with project completion targeted well before the contractual completion date of October 2010._x000D_
Due to the local geology, in particular the hard Brisbane tuff and neranleigh-fernvale formation, a combination of tunnel excavation methods are used. The majority of the tunnel is excavated by two tunnel boring machines which have a rate of progress of 16 - 20 m per day in rock having a compressive strength of between 80 and 150 MPa. Ten roadheaders operate at a rate of up to 2 m per day excavating the remaining tunnels, such as ramps, access tunnels, cross passages and merges._x000D_
The tunnel team are managing the challenges and complexities associated with tunnelling through the hard Brisbane rock. A major challenge arose during the planning of the initial mainline excavation underneath the Royal National Association Showground in Bowen Hills. This section contains low rock cover and historical maps indicate that the showground is located within a former topographic depression (alluvial valley), which a creek once flowed through.Due to traffic merge design requirements, both tunnel boring machine (TBM) and roadheader excavation methods were required to be used in this challenging geological profile. The answer was to stabilise the alluvium above both TBM section tunnels from the surface prior to excavation and to operate the TBM in single shield mode with immediate grouting of annular void from the tail shield. In addition, the roadheader section of tunnel required additional support by spiles and canopy tubes installed from the tunnel face.
Contributor(s):
D Meyer, F Brodbeck, N McKenzie
-
Big Diameter Tunnelling Beneath Low Rock CoverPDFThis product is exclusive to Digital library subscription
-
Big Diameter Tunnelling Beneath Low Rock CoverPDFNormal price $22.00Member price from $0.00
Fees above are GST inclusive
PD Hours
Approved activity
- Published: 2008
- PDF Size: 0.962 Mb.
- Unique ID: P200803039