Design of Steel Fibre Reinforced Segmental Lining for the Gold Coast Desalination Tunnels

This paper describes the design of the steel fibre reinforced precast concrete (SFRC) segmental lining for the intake and discharge tunnels for the Gold Coast desalination plant in Queensland. In addition, the key design requirements and design methods for the lining of these 2 km long, 2.8 m internal diameter tunnels, including structural, durability and maintenance requirements are discussed. Details of the segment configuration and erection process are presented along with information on the manufacture and trial testing of the concrete for the segments. The paper also gives a brief introduction to steel fibre reinforced concrete behaviour._x000D_
Construction of the tunnels commenced in April 2007, and the authors believe this is the first application of this technology in Australia.
Return to parent product
  • Design of Steel Fibre Reinforced Segmental Lining for the Gold Coast Desalination Tunnels
    PDF
    This product is exclusive to Digital library subscription
  • Design of Steel Fibre Reinforced Segmental Lining for the Gold Coast Desalination Tunnels
    PDF
    Normal price $22.00
    Member price from $0.00
    Add to cart

    Fees above are GST inclusive

PD Hours
Approved activity
  • Published: 2008
  • PDF Size: 0.976 Mb.
  • Unique ID: P200803060

Our site uses cookies

We use these to improve your browser experience. By continuing to use the website you agree to the use of cookies.