Hydraulic Fill at Osborne Mine
Osborne Mine commenced hydraulic filling of three stopes in April 1999. Two of these stopes experienced barricade failures in July 1999 and January 2000. As a result, a review of hydraulic filling was commissioned in April 2000. The design of a trial of revised specifications and practices is in the final stages, prior to the trial commencing in mid-2002.
Contributor(s):
A C Brady, J A Brown
-
Hydraulic Fill at Osborne MinePDFThis product is exclusive to Digital library subscription
-
Hydraulic Fill at Osborne MinePDFNormal price $22.00Member price from $0.00
Fees above are GST inclusive
PD Hours
Approved activity
- Published: 2002
- PDF Size: 0.544 Mb.
- Unique ID: P200205022