Skip to main content
Conference Proceedings

EXPLO 99

Conference Proceedings

EXPLO 99

PDF Add to cart

The Use of Computer Based Blasting Models in Mine Feasibility Analyses

The aim of these analyses was to utilise the latest available production information for the Wandoo operation to determine the optimal blasting parameters, costing information and predicted results (fragmentation, muckpile shape and vibration). Much of the data used as input was made available from the information gathered during the excavation of the test pits during 1995. As with any planning stage' analyses, many assumptions were required to fill gaps in the available data. The calibration of computer blasting models was conducted using data from the last of the test pit blasts (this blast was carried out in material that closely resembled rock expected to constitute the bulk of the base case design pit). This calibration was refined using observation and experience based judgements to extend the accuracy of the predictions as far as possible. All the simulations were performed assuming that the blastholes will be wet (as instructed by BGM). This has consequently determined that the appropriate explosive for the simulations and the actual blasting will be a pumped emulsion/ANFO blend. The following blast design parameters were derived by determining a likely range of powder factor (from other similar scale gold mines) with a median value of 0.62 kg/m 3 being the powder factor arrived at through the field optimisation process conducted during the test pit excavation. The total swell/displacement percentage (volume after blast/volume before blast) largely determines the diggability of a well fragmented muckpile. Consequently where fragmentation is good any reduction of total swell will probably reduce diggabilty. Any reduction of diggability can and should be traded off against increased gold recovery. In most gold mines, diggabilty will be substantially compromised at the balance which produces the most profit. When these considerations are combined with the cost to drill and blast material, processing costs and the achievement of acceptable' diggibility, the analysis becomes extremely complex and qualitative. Many trends are evident including:the relationship between powder factor (for each blast design) and maximum forward displacement (throw), see Figure 1; andthe relationship between powder factor (for each blast design) and drill and blast cost per BCM, see Figure 2. The following blast designs are matched to each of three ore-tonnage alternatives (as supplied by BGM) (Table 1). They are all based on powder factor of 0.62 kg/BCM and are considered optimum from a mining point of view'. The costing of each design includes drilling, explosives and labour cost to load, stem and tie-in holes. Using the available rock data and relying heavily on the wall exposures in the test pit(s), it is the opinion of the author that between 20 per cent to 40 per cent of the final walls excavated in the Wandoo pit would be likely to have the angle between the dominant foliation and the wall plane that is well suited to presplitting and be cost-effectively served by presplit technique. The drilling cost for 125 mm blasthole is about $11.40 per drilled metre and the cost of 40 mm presplit explosive is about $140 per 25 kg (17 metre) case. This implies that the cost to drill and blast presplit on the above parameters would be about $10.90 per square metre of presplit face. The remaining wall area would be most cost-effectively delineated using modified production blasting techniques. This requires the use of modified parameters such as smaller hole diameters, smaller spacing/ burden, higher powder factor, free face firing, less rows per blast and longer delays. These altered blast parameters would usually be applied uniformly across the entire blast fired adjacent to the wall and this trim' blast would relieve burden away from the wall, into the pit. In simplest terms, this method relies upon maximised burden relief to minimise blast energy applied to the wall. It is only applicable where the material to be blasted is waste since the throw achieved is inconsistent with ore dilution control. The largest charge weight per hole for these analyses is 360 kg and the nearest domestic structure to the proposed Wandoo pit is about 6100 metres distant. From these parameters and assuming a worst case example of rock controlled site factor, the predicted ground vibration is 0.5 mm/sec that is about five per cent of the lower limit set down in AS 2187 part two (1993). This suggests that for the current location of neighbours, ground vibration will not be an issue for the Wandoo operation.
Return to parent product
  • The Use of Computer Based Blasting Models in Mine Feasibility Analyses
    PDF
    This product is exclusive to Digital library subscription
  • The Use of Computer Based Blasting Models in Mine Feasibility Analyses
    PDF
    Normal price $22.00
    Member price from $0.00
    Add to cart

    Fees above are GST inclusive

PD Hours
Approved activity
  • Published: 1999
  • PDF Size: 0.438 Mb.
  • Unique ID: P199905016

Our site uses cookies

We use these to improve your browser experience. By continuing to use the website you agree to the use of cookies.