Design, Construction and Commissioning of A 4 Tonne/Hour Matte Fuming Pilot Plant
Aberfoyle Limited operated a matte fuming pilot plant, incorporating a SIROSMELT furnace in 1980/81. This plant was a significant advance in both smelting and tin extraction technology. Important design, construction and commissioning aspects are discussed and some of the key points to emerge from this phase of the work are reviewed.
Contributor(s):
R L Biehl, D S Conochie, K A Foo, B W Lightfoot
-
Design, Construction and Commissioning of A 4 Tonne/Hour Matte Fuming Pilot PlantPDFThis product is exclusive to Digital library subscription
-
Design, Construction and Commissioning of A 4 Tonne/Hour Matte Fuming Pilot PlantPDFNormal price $22.00Member price from $0.00
Fees above are GST inclusive
PD Hours
Approved activity
- Published: 1984
- PDF Size: 0.253 Mb.
- Unique ID: P198401014