Conference Proceedings
First Extractive Metallurgy Operators' Conference
Conference Proceedings
First Extractive Metallurgy Operators' Conference
The New Anglo Platinum Converting Project
Anglo Platinum is the world's largest producer of platinum group metals, and also produces large quantities of nickel, copper and cobalt at its Refining complex in Rustenburg, South Africa._x000D_
In 1995 Anglo Platinum embarked on a smelter modernisation project, primarily to reduce site emissions to below the guideline limit of 20 tonnes per day SO2, but also to increase the converting capacity in line with future projected production profiles._x000D_
To achieve these requirements the existing Pierce Smith converters were replaced with a single large Ausmelt converter and a new acid plant. This was the first time that an Ausmelt furnace had been used for converting, but it had the advantages of being a very robust furnace and was fully enclosed, giving good gas capture. It was thus considered the most appropriate technology from both a process and an environmental perspective. It also enabled the smelting and converting furnaces to be decoupled._x000D_
The plant was commissioned from late 2001 and the first tap was in June 2002. Despite being a new technology, ramp-up has been similar to other large scale pyrometallurgical operations. Numerous process improvements have been made since start-up, most notably a change from two-stage batch to fully continuous, resulting in the plant now operating above design in terms of throughput. Optimisation of freeboard accretion control was also a major component of the ramp-up activity._x000D_
This paper discusses the commissioning and ramp-up issues of the new Ausmelt converting furnace, concentrating on the design and process changes, and summarises current operating performance against the original design objectives.
In 1995 Anglo Platinum embarked on a smelter modernisation project, primarily to reduce site emissions to below the guideline limit of 20 tonnes per day SO2, but also to increase the converting capacity in line with future projected production profiles._x000D_
To achieve these requirements the existing Pierce Smith converters were replaced with a single large Ausmelt converter and a new acid plant. This was the first time that an Ausmelt furnace had been used for converting, but it had the advantages of being a very robust furnace and was fully enclosed, giving good gas capture. It was thus considered the most appropriate technology from both a process and an environmental perspective. It also enabled the smelting and converting furnaces to be decoupled._x000D_
The plant was commissioned from late 2001 and the first tap was in June 2002. Despite being a new technology, ramp-up has been similar to other large scale pyrometallurgical operations. Numerous process improvements have been made since start-up, most notably a change from two-stage batch to fully continuous, resulting in the plant now operating above design in terms of throughput. Optimisation of freeboard accretion control was also a major component of the ramp-up activity._x000D_
This paper discusses the commissioning and ramp-up issues of the new Ausmelt converting furnace, concentrating on the design and process changes, and summarises current operating performance against the original design objectives.
Contributor(s):
P Viviers, K Hines
-
The New Anglo Platinum Converting ProjectPDFThis product is exclusive to Digital library subscription
-
The New Anglo Platinum Converting ProjectPDFNormal price $22.00Member price from $0.00
Fees above are GST inclusive
PD Hours
Approved activity
- Published: 2005
- PDF Size: 0.533 Mb.
- Unique ID: P200509016