Morning Star Gold aims to enter the ranks of Australia's gold producers, revitalising the Eastern Victorian Goldfi elds in the second half of 2010 - the fi rst gold production in around 50 years from the Morning Star Gold mine, which was once Australia's largest under WMC. This presentation will outline the redevelopment of the Morning Star Gold Mine from exploration to production._x000D_
Morning Star Gold NL's (MCO) key project area is centred at the historic mining town of Woods Point and nearby Matlock (to the southeast) and Gaffney's Creek (to the northwest), all of which are located in the lower part of the Victorian Alps roughly 60 kms south of Mansfield. Morning Star has literally numerous historic mines and gold bearing dykes' on its tenements, many with a rich production history of high-grade gold from quartz reefs and alluvial sources._x000D_
The area encompassing the Woods Point goldfi eld and the multiple high-grade gold bearing dyke structures located north towards Jamieson and south towards Walhalla formed one of the most significant mining fields in Australian history._x000D_
Historical gold production was at least 155 t or around six million ounces of over a century of mining with an average production grade exceeding 27 g per tonne. The bulk of this recorded production came from just a handful of mines and of those only three were mined to any great depth._x000D_
One of the key historical production hubs in this area was the famous Morning Star' mine, which is situated adjacent to Woods Point township. The Morning Star mine produced almost one million ounces at 27 grams per tonne, operating fairly continuously between 1861 and 1959 with a break after Jan 1939 due to the devastating Black Friday' bush fi res across eastern Victoria._x000D_
During the early 1940s, the Morning Star was Australia's biggest gold mine. The Morning Star mine along with Walhalla ensured that this goldfield was third behind Bendigo and Ballarat as Victoria's biggest hardrock gold production centre._x000D_
Morning Star Gold has rebuilt its 100 per cent owned Morning Star' mine with a view to producing gold in the second half of 2010. Morning Star is exploring its regional dykes in order to estimate an overall gold endowment and rank local production sources to feed its proposed mill at the Morning Star mine site. Key initial targets (all within 11 kms of the Morning Star mine) are the Waverly, All Nations, Rose of Denmark, Hunts, Wallaby and Loch Fyne dykes, all of which historically produced high grade gold, much of it gained from only shallow workings above the water table in the weathered zone of rocks._x000D_
Historically the Morning Star mine was developed over 24 levels to a depth of 940 m via one large vertical shaft and a smaller, deeper inclined shaft at the 1900 feet level underground. At present MCO has dewatered and completely refurbished all infrastructure to the ten level (~310 m below surface). MCO knows there are a number of substantially under-explored and undeveloped or partially developed but not stoped areas within the Morning Star mine. As a result, MCO has been carrying out extensive channel sampling and an underground diamond drilling program targeting areas of the mine that were largely unexplored and undeveloped by the last operators of the mine - Western Mining Corp Ltd (Gold Mines of Australia). Four thousand, fi ve hundred pages of archival WMC records have helped the cause significantly._x000D_
The shaft refurbishment and reconstruction stage is complete. This has been a program that originally commenced back in 1993 and has cost around $22 M. This refurbishment paved the way for the extensive underground resource focused diamond drilling program, which MCO completed in 2008 with two company-owned and operated drill rigs from drill cuddies on level 9 (900 feet underground) of the mine. This drilling, which encountered some stunning grades intersections and multiple visible gold hits, has outlined further production opportunities including 0.4 m @ 1392 g/t Au (MS 410)._x000D_
Metallurgical testing conducted by Gekko Systems of samples obtained from the exploration program found gravity concentration and a leach circuit gave recoveries of ~95 per cent to 99 per cent, or ~92 per cent from gravity alone at a coarse crush (300 m). Currently, the plan is to use gravity to fi rstly produce dore bars on-site from the free milling gold and secondly a saleable concentrate for CIL processing off-site. A purpose built 10 t/h (~80 000 t/a) gravity treatment plant was subsequently ordered from Gekko and is expected to be installed onsite and commissioned in the Q3 2010. The plant features fi ne crushing with a vertical shaft impactor, followed by gold concentration by inline pressure jig, inline spinner and Wilfley table._x000D_
This is an ABSTRACT ONLY. No paper was prepared for this presentation.
Return to parent product
PD Hours
Approved activity
  • Published: 2010