Successful Risk Management Through Project Life Cycle for Removal of the Crown Pillar at the Marvel Loch Underground Mine
St Barbara's Marvel Loch operations have successfully used longhole open stoping as the primary mining method for a number of years. A transition to Core and Shell mining was implemented in 2009 to recover substantial ore grade resources remaining in sill and rib pillars. The transition to core and shell for the Exhibition lode required continuous waste filling of created voids and thus the removal of the crown pillar at the base of the Exhibition pit by blasting. Access to the top of pillar was denied as the pit was partially rock filled with waste rock from underground development.Beyond the technical challenges of the blasting project, a simple and transparent risk management process was developed to ensure appropriate controls and mitigating strategies were in place to minimise risk to personnel during the pillar removal process.Although failure of the crown pillar was anticipated but with the actual timing unknown, on 25 December 2011 the crown pillar yielded during normal mine operations. Engineered and isolation controls in place at the time were of a sufficiently high standard to ensure limited exposure of the underground workforce and minimal damage to mine infrastructure. Successful risk management through implementation of appropriate controls during the project lifecycle of two years and three months proved to be fundamental to the safe removal of the crown pillar.CITATION:Barrie, S C, 2012. Successful risk management through project life cycle for removal of the crown pillar at the Marvel Loch Underground Mine, in Proceedings International Mine Management 2012, pp 125-134 (The Australasian Institute of Mining and Metallurgy: Melbourne).
Contributor(s):
S C Barrie
-
Successful Risk Management Through Project Life Cycle for Removal of the Crown Pillar at the Marvel Loch Underground MinePDFThis product is exclusive to Digital library subscription
-
Successful Risk Management Through Project Life Cycle for Removal of the Crown Pillar at the Marvel Loch Underground MinePDFNormal price $22.00Member price from $0.00
Fees above are GST inclusive
PD Hours
Approved activity
- Published: 2012
- PDF Size: 0.459 Mb.
- Unique ID: P201211013