Skip to main content

The AusIMM office is closed for the end of year break until Monday 6 January 2025. Please note members can pay their renewals online at ausimm.com/renew, and hardcopy publication orders will be processed on our return. We wish you a safe and happy festive season.

Conference Proceedings

Life of Mine Conference 2023

Conference Proceedings

Life of Mine Conference 2023

PDF Add to cart

Diavik Diamond Mine north country rock pile – an example of integrated mine planning for successful progressive reclamation

Rio Tinto has actively committed to progressive reclamation, concurrent with commercial operations, at its Diavik Diamond Mine. The most significant piece of progressive reclamation undertaken at Diavik to date has been the construction of an engineered thermal rock cover for the mine’s largest waste rock storage area. This 80-metre-tall and 2000-metre-long area is known as the Waste Rock Storage Area – North Country Rock Pile (WRSA-NCRP) and contains the operationally segregated potentially acid-generating waste rock mined over the last 20 years. As part of the mine plan, an opportunity was recognised where a limited 1.5 per cent of the WRSANCRP surface area was required for storage of the balance of life-of-mine generated waste rock and a decision was made to advance the closure design almost a decade ahead of final closure. With over 12 860 000 tonnes of material placed and 57 443 dozer hours logged since cover construction, progressive reclamation on the WRSA-NCRP is scheduled to be complete in mid-2023, three years before planned cessation of commercial operations in 2026. The progressive closure of the WRSA-NCRP demonstrates Rio Tinto’s commitment to not only closure, but modern best practices with integrated mine closure. Over the past seven years, Diavik has overcome multiple implementation hurdles for this project including the psychology of operational standby, the financial mechanisms required to support closure, working within the constraints of a mine plan and the associated operational organisational structures. This paper outlines the lessons learned to provide an example of successful integrated mine planning for closure. The North Country Rock Pile project had three major learnings which resulted in an effective organisational structure that allowed for the execution of an integrated planning model for progressive closure. The initial hurdle the project faced was adapting the psychology of an operational open pit mining team. The team was an experienced mining group who came in with the perspective to target the shortest haul possible resulting in the initial perception that the longer haul of material to the NCRP was an un-necessary task impacting operational performance metrics. After the installation of an improved dispatch tracking system and performance metrics, it was possible to demonstrate that the mine was shovel constrained. This showcased the short haul was generating an increase in queue time not production. With updated performance metrics, the team was aligned to target a decrease standby through haulage to the NCRP. These performance metrics had to be reinforced by financial mechanisms. The operations team was able to offset costs by charging time to the capital project set-up for the closure of the NCRP. This allowed the operations team to receive credit for time that would have otherwise likely been standby. As well, the progressive closure project was able to receive the benefit of not having to incur costs for the drill, blast and load as that was done as part of the operation. This was a significant benefit to the project and one of the primary drivers for the early approvals of the work as the project costs were limited to the incremental haulage distance and placement of the material. Life of Mine Conference 2023 | Brisbane, Australia | 2–4 August 2023 114 While the combined operational and progressive closure approach provided financial advantages, it did result in the project being constrained by the operational activities. A traditional capital project is managed through a linear execution plan where the deliverables within a project are within the realm of control of the project execution team. However, the NCRP project had to be continuously adapted to the outcomes of the pit operations. This included geotechnical constraints, ore delivery, and other operational delays. To adapt, the planning module had to be dynamic but not reactive to allow for adjustments on a shift-by-shift basis. Based on this requirement the Diavik Closure Projects structure adopted a mine planning format. The team executed a similar planning timeline and reporting structure as the mine operations team, allowing planning to be integrated into the operational planning structures on a daily, weekly, monthly and quarterly basis. This resulted in the Projects team as a core pillar of the mine planning team. The process of continuous improvement spanned six years and has resulted in the project being ahead of schedule and under budget for the project’s scheduled progressive closure completion date of June 2023.
The North Country Rock Pile project supports the argument that bulk earthworks progressive closure projects should be integrated into the operational mine plan. If the project is aligned the mine plan it allows for dynamic adjustments which capitalise on evolving opportunities inevitable in an operating mine. These cultural and organisational alignments should be supported by appropriate performance metrics and financial mechanisms to ensure united priorities. The result of this alignment provides long-term financial savings for the business as well as delivery of closure objectives.
Return to parent product
  • Diavik Diamond Mine north country rock pile – an example of integrated mine planning for successful progressive reclamation
    PDF
    This product is exclusive to Digital library subscription
  • Diavik Diamond Mine north country rock pile – an example of integrated mine planning for successful progressive reclamation
    PDF
    Normal price $22.00
    Member price from $0.00
    Add to cart

    Fees above are GST inclusive

PD Hours
Approved activity
  • Published: 2023
  • Pages: 2
  • PDF Size: 0.651 Mb.
  • Unique ID: P-03248-S7X5N1

Our site uses cookies

We use these to improve your browser experience. By continuing to use the website you agree to the use of cookies.