Mt Isa copper concentrator cleaner circuit redesign
The Mount Isa Copper Concentrator was commissioned in 1973. Since commissioning some significant upgrades have been undertaken such as:_x000D_
the replacement of the rod mill/ball mill circuit with AG mills and the subsequent conversion of the AG mills to SAG Mills._x000D_
the introduction of columns as retreat cleaners in 1987, then reallocated as prefloat cleaners in 1994 and rougher cleaners in 1996. the repurposing of some rougher capacity to preflotation roughing to remove carbonaceous pyrite and talc in 1994. the introduction of a Jameson Cell for preflotation cleaning in 2000._x000D_
the expansion of the rougher and cleaner circuits in 2002 with the inclusion of 6 x 100 m3 Wemco cells to replace the capacity lost to preflotation and to increase residence time and improve recovery. In 2013 work commenced to replace the cleaner circuit after 40 years of operation. The new cleaner circuit, consisting of 3 x B5400/18 Jameson Cells, replaced the rougher cleaner columns, cleaners, recleaners and retreat Agitair banks and was commissioned in Sep 2015. The new cleaner circuit was configured as two cells in series producing the final concentrate and a cleaner scavenger cell to supplement the existing Wemco cleaner scavenger cells. The performance of the new circuit is discussed.CITATION:Lawson, V, Muller, M, Radulovic, P and Wallace, J, 2017. Mt Isa copper concentrator cleaner circuit redesign, in Proceedings MetPlant 2017, pp 279-287 (The Australasian Institute of Mining and Metallurgy: Melbourne).
the replacement of the rod mill/ball mill circuit with AG mills and the subsequent conversion of the AG mills to SAG Mills._x000D_
the introduction of columns as retreat cleaners in 1987, then reallocated as prefloat cleaners in 1994 and rougher cleaners in 1996. the repurposing of some rougher capacity to preflotation roughing to remove carbonaceous pyrite and talc in 1994. the introduction of a Jameson Cell for preflotation cleaning in 2000._x000D_
the expansion of the rougher and cleaner circuits in 2002 with the inclusion of 6 x 100 m3 Wemco cells to replace the capacity lost to preflotation and to increase residence time and improve recovery. In 2013 work commenced to replace the cleaner circuit after 40 years of operation. The new cleaner circuit, consisting of 3 x B5400/18 Jameson Cells, replaced the rougher cleaner columns, cleaners, recleaners and retreat Agitair banks and was commissioned in Sep 2015. The new cleaner circuit was configured as two cells in series producing the final concentrate and a cleaner scavenger cell to supplement the existing Wemco cleaner scavenger cells. The performance of the new circuit is discussed.CITATION:Lawson, V, Muller, M, Radulovic, P and Wallace, J, 2017. Mt Isa copper concentrator cleaner circuit redesign, in Proceedings MetPlant 2017, pp 279-287 (The Australasian Institute of Mining and Metallurgy: Melbourne).
Contributor(s):
V Lawson, M Muller, P Radulovic, J Wallace
-
Mt Isa copper concentrator cleaner circuit redesignPDFThis product is exclusive to Digital library subscription
-
Mt Isa copper concentrator cleaner circuit redesignPDFNormal price $22.00Member price from $0.00
Fees above are GST inclusive
PD Hours
Approved activity
- Published: 2017
- PDF Size: 0.769 Mb.
- Unique ID: P201706020