Conference Proceedings
MetPlant 2017
Conference Proceedings
MetPlant 2017
Nui Phao mine - flotation circuit upgrade
In the current tough mining environment with lower commodity prices, operators need to improve operational profitability. Optimised equipment asset management is a sustainable way to achieve this objective. The increased efficiency of installed process equipment positively contributes to the circuit performance, affecting metallurgical performance, plant availability and operating costs. Nui Phao Mining Company Limited (NPMC) operates a polymetallic mine located in Vietnam. The circuit produces four main products, tungsten, fluorspar, bismuth and copper. Tungsten is the major revenue producer. The operation experienced the following equipment inefficiencies in its copper and bulk sulfide flotation (BSF) circuits: lower than expected metallurgical performance - the BSF rougher flotation tails contained coarse (+106 m) sulfur minerals which affected the downstream tungsten gravity circuit. The unrecovered sulfur competed with tungsten minerals affecting both tungsten recovery and product grade._x000D_
structural integrity and safety - the flotation circuit structures experienced excessive vibration beyond the acceptable tolerance levels. The vibration was attributed to the flotation mechanism design and impeller tip speeds._x000D_
equipment reliability and wear life issues - the flotation mechanisms were being replaced every six months, with reported failures at three months. This resulted in high operational costs. A mineralogical evaluation of the ore indicated that the coarse sulfur minerals were well liberated and relatively rich in pyrrhotite and pyrite. It was predicted that these particles should be recoverable by flotation under optimum conditions. NPMC worked collaboratively with Outotec to investigate options to improve the metallurgical performance of both sulfur and tungsten. A review of the copper and BSF rougher circuit infrastructure was also undertaken and focused on reducing the structural vibration and improving mechanism wear life. Prior to the circuit upgrade, laboratory and pilot testing was conducted to validate the circuit improvements. The final solution included the installation of Outotec FloatForce mechanisms in the existing copper and BSF rougher circuits, and a new flash circuit (SkimAir) treating the rougher tails stream ahead of the tungsten gravity circuit. The flash circuit is unique, as typically these types of cells are installed in grinding circuits. By March 2016, all circuit upgrades were complete, however the initial metallurgical performance was below expectations. NPMC and Outotec worked together to investigate and improve performance through further equipment modifications. Since October 2016, the metallurgical performance has improved significantly. Coarse sulfur mineral recovery has improved, resulting in an overall increase in recovery of sulfur and tungsten of 4.7% and 2.7% respectively. The Outotec FloatForce mechanism has also delivered operational benefits, with a reduction in structural vibration to within acceptable levels (<4.0 mm s) and an improvement in mechanism wear life by 150%. this paper discusses the bsf circuit upgrades and compares operational data before and after the upgrade to quantify the improvements in metallurgical performance, structural vibration and mechanism wear life. citation:morgan, s, weekes, b, jakowetz, a, litson, s, taylor, s, do, t l and bourke, p, 2017. nui phao mine - flotation circuit upgrade, in proceedings metplant 2017, pp 230-253 (the australasian institute of mining and metallurgy: melbourne).>4.0>
structural integrity and safety - the flotation circuit structures experienced excessive vibration beyond the acceptable tolerance levels. The vibration was attributed to the flotation mechanism design and impeller tip speeds._x000D_
equipment reliability and wear life issues - the flotation mechanisms were being replaced every six months, with reported failures at three months. This resulted in high operational costs. A mineralogical evaluation of the ore indicated that the coarse sulfur minerals were well liberated and relatively rich in pyrrhotite and pyrite. It was predicted that these particles should be recoverable by flotation under optimum conditions. NPMC worked collaboratively with Outotec to investigate options to improve the metallurgical performance of both sulfur and tungsten. A review of the copper and BSF rougher circuit infrastructure was also undertaken and focused on reducing the structural vibration and improving mechanism wear life. Prior to the circuit upgrade, laboratory and pilot testing was conducted to validate the circuit improvements. The final solution included the installation of Outotec FloatForce mechanisms in the existing copper and BSF rougher circuits, and a new flash circuit (SkimAir) treating the rougher tails stream ahead of the tungsten gravity circuit. The flash circuit is unique, as typically these types of cells are installed in grinding circuits. By March 2016, all circuit upgrades were complete, however the initial metallurgical performance was below expectations. NPMC and Outotec worked together to investigate and improve performance through further equipment modifications. Since October 2016, the metallurgical performance has improved significantly. Coarse sulfur mineral recovery has improved, resulting in an overall increase in recovery of sulfur and tungsten of 4.7% and 2.7% respectively. The Outotec FloatForce mechanism has also delivered operational benefits, with a reduction in structural vibration to within acceptable levels (<4.0 mm s) and an improvement in mechanism wear life by 150%. this paper discusses the bsf circuit upgrades and compares operational data before and after the upgrade to quantify the improvements in metallurgical performance, structural vibration and mechanism wear life. citation:morgan, s, weekes, b, jakowetz, a, litson, s, taylor, s, do, t l and bourke, p, 2017. nui phao mine - flotation circuit upgrade, in proceedings metplant 2017, pp 230-253 (the australasian institute of mining and metallurgy: melbourne).>4.0>
Contributor(s):
S Morgan, B Weekes, A Jakowetz, S Litson, S Taylor, T L Do, P Bourke
-
Nui Phao mine - flotation circuit upgradePDFThis product is exclusive to Digital library subscription
-
Nui Phao mine - flotation circuit upgradePDFNormal price $22.00Member price from $0.00
Fees above are GST inclusive
PD Hours
Approved activity
- Published: 2017
- PDF Size: 1.52 Mb.
- Unique ID: P201706017