Conference Proceedings
MINEFILL '98 - The Sixth International Symposium on Mining with Backfill, Brisbane, Qld, April
Conference Proceedings
MINEFILL '98 - The Sixth International Symposium on Mining with Backfill, Brisbane, Qld, April
The Implementation of Paste Fill at the Henty Gold Mine
The Henty Gold Mine, located in Western lasiuania use, uuiusatise solutions to effectively manage a mining operation in an environmentally sensitive setting and has been presented with several environmental awards. Fill is required as part of the mining method to provide passive ground support, minimise rock exposure and ensure maximum recovery of the small but high-grade orebody. The use of the whole portion of leach residue in the backfill reduces the surface tailing disposal requirements. Therefore, High Density Paste Fill (HDPF) has been selected as the most appropriate fill method to meet these objectives._x000D_
Additional benefits include the minimisation of excess water from fill and the subsequent need for the collection and treatment of water and slimes. There are minimal equipment requirements during placement, thereby optimising mine resources for production. The initial paste fill design was based on the Bad Grund and Ranunelsberg Mines paste fill systems of Preussag in Germany and comprised pumping filtered tailings paste some 1.2 kin uphill from the mill to the mine portal, where cement was to be added before being distributed underground. The system was designed following initial testwork that was undertaken on a bulk sample of ore mined from the scar surface Sill Zone. Subsequently, during the mining of the Zone 96 orehody, it was found that there were significant mineralogical variations in the composition of the ore mined. Following processing, the resultant Icach residue caused significant changes in the paste rheology and therefore the pump and flow characteristics. An alternative solution was implemented that involved the use of agitator trucks to transport the cemented paste to the portal. This required modifications to the fill preparation system and also the underground distribution system. Laboratory strength tests of the HDPF using actual gold plant leach residue showed low early strengths were attained with HDPF containing only filtered leach residue. Therefore, high binder addition rates or an increase in the fill cycle time would be required to allow the fill to gain sufficient strength. A considerable amount of potentially acid generating waste rock also requires underground disposal. By blending the waste rock with the HDPF, the strengths were improved and the required cement addition rate reduced by about one-half. The potentially acid funning waste rock is encapsulated in the highly alkaline cemented paste, minimising the potential for acid generation.
Additional benefits include the minimisation of excess water from fill and the subsequent need for the collection and treatment of water and slimes. There are minimal equipment requirements during placement, thereby optimising mine resources for production. The initial paste fill design was based on the Bad Grund and Ranunelsberg Mines paste fill systems of Preussag in Germany and comprised pumping filtered tailings paste some 1.2 kin uphill from the mill to the mine portal, where cement was to be added before being distributed underground. The system was designed following initial testwork that was undertaken on a bulk sample of ore mined from the scar surface Sill Zone. Subsequently, during the mining of the Zone 96 orehody, it was found that there were significant mineralogical variations in the composition of the ore mined. Following processing, the resultant Icach residue caused significant changes in the paste rheology and therefore the pump and flow characteristics. An alternative solution was implemented that involved the use of agitator trucks to transport the cemented paste to the portal. This required modifications to the fill preparation system and also the underground distribution system. Laboratory strength tests of the HDPF using actual gold plant leach residue showed low early strengths were attained with HDPF containing only filtered leach residue. Therefore, high binder addition rates or an increase in the fill cycle time would be required to allow the fill to gain sufficient strength. A considerable amount of potentially acid generating waste rock also requires underground disposal. By blending the waste rock with the HDPF, the strengths were improved and the required cement addition rate reduced by about one-half. The potentially acid funning waste rock is encapsulated in the highly alkaline cemented paste, minimising the potential for acid generation.
Contributor(s):
A Henderson, G Jardine, C Woodall
-
The Implementation of Paste Fill at the Henty Gold MinePDFThis product is exclusive to Digital library subscription
-
The Implementation of Paste Fill at the Henty Gold MinePDFNormal price $22.00Member price from $0.00
Fees above are GST inclusive
PD Hours
Approved activity
- Published: 1998
- PDF Size: 1.461 Mb.
- Unique ID: P199801046