The Hellyer Mine - Feasibility to Production with Confidence

For its Hellyer project, Aberfoyle sought to establish a high degree of confidence in all aspects of the feasibility study. Accurate capital and operating cost estimates were an integral and essential part of the study._x000D_
They were crucial to the evaluation of investment returns and competitive cost position. Both the capital and operating cost estimates were based on the comprehensive data available from exploratory mine development, pilot plant operation, detailed engineering design, and Aberfoyle's experience in the area. One of the principal project objectives was to maximise operating productivity and efficiencies and this created capital cost alternatives which needed thorough cost-benefit assessment. The estimated capital cost for construction and development was $90 million, and the project was completed virtually on time for $80 million. The first year's experience indicated that operating costs would settle to well within 10% of the estimates.
Return to parent product
  • The Hellyer Mine - Feasibility to Production with Confidence
    PDF
    This product is exclusive to Digital library subscription
  • The Hellyer Mine - Feasibility to Production with Confidence
    PDF
    Normal price $22.00
    Member price from $0.00
    Add to cart

    Fees above are GST inclusive

PD Hours
Approved activity
  • Published: 1990
  • PDF Size: 1.091 Mb.
  • Unique ID: P199004021

Our site uses cookies

We use these to improve your browser experience. By continuing to use the website you agree to the use of cookies.