Skip to main content
Conference Proceedings

Ninth AusIMM Open Pit Operators' Conference 2016

Conference Proceedings

Ninth AusIMM Open Pit Operators' Conference 2016

PDF Add to cart

A Case Study on the Assessment, Planning and Extraction of the Crown Pillar at Sunrise Dam Gold Mine

Sunrise Dam Gold Mine (SDGM) is located 820 km from Perth, 220 km from Kalgoorlie-Boulder and 55 km south of Laverton in Western Australia. The SDGM main pit had successfully operated since 1997 and was due to be completed during 2012. An opportunity existed to extract the high-grade crown pillar - 600 kt @ 7 g/t for 135 koz by either open pit or underground methods._x000D_
The crown pillar was the 60 m (vertically) thick remaining part of the high-grade Cosmo orebody between the top of the paste filled underground mine stopes and the planned base of the final open pit shell._x000D_
There were two major difficulties being considered when choosing the underground or open pit options: a major wall failure in the upper section of the main pit wall directly above the crown pillar restricting access from the base of the open pit to the top of the crown pillarimpact of a high rainfall event while the crown pillar was being mined from either surface or underground resulting in flooding of the underground mine workings.This paper will discuss the following issues:the process to identify and evaluate the risks in both options using knowledge based modelling software; this technique allowed the evaluation of a complex set of assumptions to arrive at the preferred optionremediation of the Watu failurethe selection of the preferred option and the challenges encountered before, during and after the extraction of the crown pillarthe planning and geotechnical work to ensure the safe extraction of the crown pillarsuccessful outcomes transitioning from open pit operation to a solely underground operation._x000D_
Citation: Robeson, A, Cowan, M and Brockman, M, 2016. A Case Study on the Assessment, Planning and Extraction of the Crown Pillar at Sunrise Dam Gold Mine, in Proceedings Ninth AusIMM Open Pit Operators' Conference 2016, pp115-136 (The Australasian Institute of Mining and Metallurgy: Melbourne).
Return to parent product
  • A Case Study on the Assessment, Planning and Extraction of the Crown Pillar at Sunrise Dam Gold Mine
    PDF
    This product is exclusive to Digital library subscription
  • A Case Study on the Assessment, Planning and Extraction of the Crown Pillar at Sunrise Dam Gold Mine
    PDF
    Normal price $22.00
    Member price from $0.00
    Add to cart

    Fees above are GST inclusive

PD Hours
Approved activity
  • Published: 2016
  • PDF Size: 2.55 Mb.
  • Unique ID: P201609013

Our site uses cookies

We use these to improve your browser experience. By continuing to use the website you agree to the use of cookies.