Gold mineralisation at Bendigo is exclusively associated with quartz reefs, commonly found within or near anticlinal fold hinges. The gold is typically coarse grained (0.5 mm to 5 mm), free milling and displays a complex, nuggetty distribution within the veins._x000D_
This ore is highly amenable to gravity recovery processes. As the Bendigo operation is not permitted to treat whole ore by a cyanide leach/CIL circuit, the flow sheet is more complex than conventional gold recovery circuits. Primary gold recovery is from a gravity circuit closing the grinding circuit to a bulk gravity concentrate and from a flotation circuit treating cyclone overflow to a bulk float concentrate. The plant capacity is relatively low by current gold industry standards at 600 000 tpa._x000D_
Re-establishing gold production at Bendigo has presented several challenging, and sometimes competing, issues in process design and operation. The mine, process plant, associated services and infrastructure are at Kangaroo Flat, a low density, semi-rural zone in the southern urbanisation of the Bendigo metropolitan area._x000D_
One of the main processing challenges during the design was the competing comminution requirement to avoid over-grinding, which would flatten or smear the characteristic nugget gold and hinder effective gravity gold recovery, whilst also providing sufficiently well liberated particles that would respond well to flotation._x000D_
Important, non-metallurgical challenges were to minimise impacts on the local community from noise, dust, air emissions, visual impact, water egress and off-site traffic.
Return to parent product
  • Process Design Aspects at Bendigo Mining's Gold Operations
    PDF
    This product is exclusive to Digital library subscription
  • Process Design Aspects at Bendigo Mining's Gold Operations
    PDF
    Normal price $22.00
    Member price from $0.00
    Add to cart

    Fees above are GST inclusive

PD Hours
Approved activity
  • Published: 2006
  • PDF Size: 1.04 Mb.
  • Unique ID: P200701023

Our site uses cookies

We use these to improve your browser experience. By continuing to use the website you agree to the use of cookies.