The Amacan Copper Project
The Amacan Copper Project was constructed in the Philippines by a Finnish-Filipino Consortium during the years 1979 - 1982. The project involved a turnkey contract for a mine and a concentrator to process 25 000 tonne per day of porphy- ritic copper ore at a grade of 0.45% Cu._x000D_
The orebody is located on Mindanao, the southernmost island of the Philippines, in rugged, mountainous terrain approximately 1 000 m above sea level. The adopted design principle was based on an efficient, straightforward installation utilising a minimum number of items of equipment each with high unit capacities. The consortium faced many problems which resulted in lengthy delays in construction and finally led to the client taking over responsibility for the completion of the project. The concentrator was successfully commissioned in July 1982.
The orebody is located on Mindanao, the southernmost island of the Philippines, in rugged, mountainous terrain approximately 1 000 m above sea level. The adopted design principle was based on an efficient, straightforward installation utilising a minimum number of items of equipment each with high unit capacities. The consortium faced many problems which resulted in lengthy delays in construction and finally led to the client taking over responsibility for the completion of the project. The concentrator was successfully commissioned in July 1982.
Contributor(s):
M Autio
-
The Amacan Copper ProjectPDFThis product is exclusive to Digital library subscription
-
The Amacan Copper ProjectPDFNormal price $22.00Member price from $0.00
Fees above are GST inclusive
PD Hours
Approved activity
- Published: 1986
- PDF Size: 0.627 Mb.
- Unique ID: P198605019