Conference Proceedings
Seventh Large Open Pit Conference 2010
Conference Proceedings
Seventh Large Open Pit Conference 2010
Minimising Crest Loss by Eliminating Surface Dilation Due to Presplitting
In most mines using presplitting the final excavated wall shows a zone of damage just below the crest and well defined presplit half barrels._x000D_
The crest damage (surface dilation) zone varies and is added to by subsequent adjacent perimeter blasting operations. Keeping the preconditioning to a minimum is possible using the methods described in this paper, developed on several diverse and geographically distant mining operations to control crest dilation and preconditioning by presplitting in advance - not just laterally but vertically in advance._x000D_
The first documented case (Delbridge, Marton and McSweeney, 2004) in the development of the concept was undertaken at AngloGold Australia Pty Ltd's Sunrise Dam Gold Mine (SDGM), located beside Lake Carey, some 730 km northeast of Perth, Western Australia. The mine had been developed in a series of cutbacks to a depth of over 300 m and began underground mining during the latter stages of open cut operations. This mine is fairly unique in that it utilised a single pass vertical presplit which initially extended over three bench heights and after the failure mechanisms were understood, over four benches. The presplit drilling for the three stacked benches started on the floor of the second bench so that any dilation was confined to the surface one bench above the crest and modified perimeter blasting was then developed to curtail damage from blasting adjacent to the new crest._x000D_
The second case is based on a South African coal mine in the Witbank Coal Measures, 140 km northeast of Johannesburg, Republic of South Africa (RSA). It was important that blasting for optimal wall stability and minimal scaling was developed in advance. A dragline is scheduled to excavate the #2 seam midburden which is the lowest of the economically viable coal seams in the five seam Witbank Coal Measures. Mining of the overburden, coal and partings above the dragline midburden pass are by excavator and truck and each mining layer is individually blasted. The results of presplitting the midburden through the overlying coal seams and partings have provided a presplit with no surface dilation of the midburden crest and ensures any subsequent crest loss is solely due to blasting adjacent to the vertical presplit. Typical of all coal mines in South Africa only vertical presplits are used._x000D_
Wall control is most commonly delivered by presplit blasting and one common sight after the dust clears is a ridge of broken blocks along the presplit row, usually with a main crack running between the presplit blastholes and often parallel cracks either side of the perimeter line. The surface rock strata or block structures have been dilated by the venting gases and shock waves. Decoupled, fully coupled, single or double deck charges are used depending on a variety of factors, anecdotal practices and perceived benefits._x000D_
Preconditioning of the crest rock by blasting from above may not be visible to the naked eye (or non-existent in overburden in strip coal mines) but the high speed venting of explosives gases (and often the water in the presplits) preferentially follow existing cracks and structures because there is no developed presplit crack near the surface. This nearly always lifts, shifts and separates the surface structures and geological layers._x000D_
Stopping the dilation by sacrificial' or in advance' presplitting has been shown to reduce the crest loss at both metal and coal mines. Drilling and presplit blasting through an upper level of bench or layer provides a degree of restraint to the target layer where the crest must be maintained and any damage caused by the venting gases will not cause concern as it is removed as planned, leaving a stable crest._x000D_
FORMAL CITATION:Marton, A, 2010. Minimising crest loss by eliminating surface dilation due to presplitting, in Proceedings Seventh Large Open Pit Conference 2010, pp 57-64 (The Australasian Institute of Mining and Metallurgy: Melbourne).
The crest damage (surface dilation) zone varies and is added to by subsequent adjacent perimeter blasting operations. Keeping the preconditioning to a minimum is possible using the methods described in this paper, developed on several diverse and geographically distant mining operations to control crest dilation and preconditioning by presplitting in advance - not just laterally but vertically in advance._x000D_
The first documented case (Delbridge, Marton and McSweeney, 2004) in the development of the concept was undertaken at AngloGold Australia Pty Ltd's Sunrise Dam Gold Mine (SDGM), located beside Lake Carey, some 730 km northeast of Perth, Western Australia. The mine had been developed in a series of cutbacks to a depth of over 300 m and began underground mining during the latter stages of open cut operations. This mine is fairly unique in that it utilised a single pass vertical presplit which initially extended over three bench heights and after the failure mechanisms were understood, over four benches. The presplit drilling for the three stacked benches started on the floor of the second bench so that any dilation was confined to the surface one bench above the crest and modified perimeter blasting was then developed to curtail damage from blasting adjacent to the new crest._x000D_
The second case is based on a South African coal mine in the Witbank Coal Measures, 140 km northeast of Johannesburg, Republic of South Africa (RSA). It was important that blasting for optimal wall stability and minimal scaling was developed in advance. A dragline is scheduled to excavate the #2 seam midburden which is the lowest of the economically viable coal seams in the five seam Witbank Coal Measures. Mining of the overburden, coal and partings above the dragline midburden pass are by excavator and truck and each mining layer is individually blasted. The results of presplitting the midburden through the overlying coal seams and partings have provided a presplit with no surface dilation of the midburden crest and ensures any subsequent crest loss is solely due to blasting adjacent to the vertical presplit. Typical of all coal mines in South Africa only vertical presplits are used._x000D_
Wall control is most commonly delivered by presplit blasting and one common sight after the dust clears is a ridge of broken blocks along the presplit row, usually with a main crack running between the presplit blastholes and often parallel cracks either side of the perimeter line. The surface rock strata or block structures have been dilated by the venting gases and shock waves. Decoupled, fully coupled, single or double deck charges are used depending on a variety of factors, anecdotal practices and perceived benefits._x000D_
Preconditioning of the crest rock by blasting from above may not be visible to the naked eye (or non-existent in overburden in strip coal mines) but the high speed venting of explosives gases (and often the water in the presplits) preferentially follow existing cracks and structures because there is no developed presplit crack near the surface. This nearly always lifts, shifts and separates the surface structures and geological layers._x000D_
Stopping the dilation by sacrificial' or in advance' presplitting has been shown to reduce the crest loss at both metal and coal mines. Drilling and presplit blasting through an upper level of bench or layer provides a degree of restraint to the target layer where the crest must be maintained and any damage caused by the venting gases will not cause concern as it is removed as planned, leaving a stable crest._x000D_
FORMAL CITATION:Marton, A, 2010. Minimising crest loss by eliminating surface dilation due to presplitting, in Proceedings Seventh Large Open Pit Conference 2010, pp 57-64 (The Australasian Institute of Mining and Metallurgy: Melbourne).
Contributor(s):
A Marton
-
Minimising Crest Loss by Eliminating Surface Dilation Due to PresplittingPDFThis product is exclusive to Digital library subscription
-
Minimising Crest Loss by Eliminating Surface Dilation Due to PresplittingPDFNormal price $22.00Member price from $0.00
Fees above are GST inclusive
PD Hours
Approved activity
- Published: 2010
- PDF Size: 7.284 Mb.
- Unique ID: P201005007