The North Western Sewer Tunnel Project - Section 3
The North Western Sewer tunnel extends over 11.5 km in the North Western suburbs of Melbourne._x000D_
The $253 million tunnel project provides a critical link in the Melbourne Sewer Network. The existing sewers fail to service the increasing demands of the growing population of the North West regions of Melbourne. This project will protect the environment and improve the standards of service of the existing system. This paper concentrates on Section three of this project, consisting of the final 4 km of the Contract, three access shafts and a cut and cover section of tunnel._x000D_
Transfield Tunnelling as Head Contractor constructed the tunnel for Melbourne Water Corporation, with Enetech Streamline, formally Streamline Australia, a trading arm of Melbourne Water acting as Superintendent._x000D_
Excavation of Section three of this project commenced in September 1994 and project completion is scheduled for October 1998. The tunnel passes below the residential suburb of Essendon, through some of the most challenging ground conditions ever attempted to be tunnelled in Australia.
The $253 million tunnel project provides a critical link in the Melbourne Sewer Network. The existing sewers fail to service the increasing demands of the growing population of the North West regions of Melbourne. This project will protect the environment and improve the standards of service of the existing system. This paper concentrates on Section three of this project, consisting of the final 4 km of the Contract, three access shafts and a cut and cover section of tunnel._x000D_
Transfield Tunnelling as Head Contractor constructed the tunnel for Melbourne Water Corporation, with Enetech Streamline, formally Streamline Australia, a trading arm of Melbourne Water acting as Superintendent._x000D_
Excavation of Section three of this project commenced in September 1994 and project completion is scheduled for October 1998. The tunnel passes below the residential suburb of Essendon, through some of the most challenging ground conditions ever attempted to be tunnelled in Australia.
Contributor(s):
A Stevenson, D Hake, R Milton, H Sprague
-
The North Western Sewer Tunnel Project - Section 3PDFThis product is exclusive to Digital library subscription
-
The North Western Sewer Tunnel Project - Section 3PDFNormal price $22.00Member price from $0.00
Fees above are GST inclusive
PD Hours
Approved activity
- Published: 1999
- PDF Size: 0.775 Mb.
- Unique ID: P199901041