Tunnelling Design on the Northside Storage Tunnel Project
The Northside Storage Tunnel Project in Sydney includes over 20 km of TBM driven tunnels, over 3 km of declines and major caverns and pump rooms. The paper describes methods used for design on the project. Emphasis is given to the refinement of the use of empirical rock mass classifications, and to the use of discontinuum numerical methods._x000D_
The use of empirical rock mass classifications in Sydney sandstone has usually led to conservative design because the systems are based on a random orientation of joints in the rockmass. Because the joint sets are usually oriented in a way that is beneficial for tunnelling, limits must be placed on the parameters used in the classifications system. The paper discusses these limits and the derivation of the parameters._x000D_
The use of numerical methods in Sydney sandstone is discussed. Continuum methods have their uses, but discontinuum methods are preferred. The use of UDEC has been validated against a previous project, the New Southern Railway. Recommendations are given for UDEC models.
The use of empirical rock mass classifications in Sydney sandstone has usually led to conservative design because the systems are based on a random orientation of joints in the rockmass. Because the joint sets are usually oriented in a way that is beneficial for tunnelling, limits must be placed on the parameters used in the classifications system. The paper discusses these limits and the derivation of the parameters._x000D_
The use of numerical methods in Sydney sandstone is discussed. Continuum methods have their uses, but discontinuum methods are preferred. The use of UDEC has been validated against a previous project, the New Southern Railway. Recommendations are given for UDEC models.
Contributor(s):
H R Asche, A Quigley
-
Tunnelling Design on the Northside Storage Tunnel ProjectPDFThis product is exclusive to Digital library subscription
-
Tunnelling Design on the Northside Storage Tunnel ProjectPDFNormal price $22.00Member price from $0.00
Fees above are GST inclusive
PD Hours
Approved activity
- Published: 1999
- PDF Size: 0.677 Mb.
- Unique ID: P199901017