Telfer Train 1 Copper Flotation Circuit Reconfiguration

Telfer is a gold/copper operation, currently operating one open pit mine and one underground mine. The ore processing plant consists of two parallel trains involving semi-autogenous mill, ball mill and crusher (SABC) grinding, flotation and leaching. Due to receiving relatively high grade underground ore for over half of its total feed, Train 1 frequently experienced cleaning circuit overloading during high production periods. This resulted in losses in recovery and ineffective concentrate upgrade._x000D_
As a quick and simple solution, the Train 1 copper flotation circuit was reconfigured to send concentrate from the first two rougher cells directly to the final concentrate and return the cleaner scavenger tailings to the third rougher cell. These modifications have resulted in a 1.4 per cent increase in plant copper recovery with no change in final concentrate grade. Preliminary results also indicate gold recovery has increased by more than 1 per cent since the circuit reconfiguration. Other benefits include less spillage, more friendly circuit to operate and a more consistent metallurgical performance._x000D_
Focus for the next phase of optimisation is on concentrate upgrade. A number of opportunities have been identified and are currently being investigated, including staged reagent addition, single stage cleaning of the first two copper rougher concentrates, regrinding of the remaining copper rougher concentrate prior to cleaning and process control based on a machine vision system.
Return to parent product
  • Telfer Train 1 Copper Flotation Circuit Reconfiguration
    PDF
    This product is exclusive to Digital library subscription
  • Telfer Train 1 Copper Flotation Circuit Reconfiguration
    PDF
    Normal price $22.00
    Member price from $0.00
    Add to cart

    Fees above are GST inclusive

PD Hours
Approved activity
  • Published: 2008
  • PDF Size: 0.391 Mb.
  • Unique ID: P200911027

Our site uses cookies

We use these to improve your browser experience. By continuing to use the website you agree to the use of cookies.