Conference Proceedings
Underground Operators Conference Proceeding 2023
Conference Proceedings
Underground Operators Conference Proceeding 2023
The application of critical chain project management to sublevel open stoping at Olympic Dam
Since 2019, the mine planning team at Olympic Dam has been establishing and maturing a shift from deterministic to probabilistic scheduling techniques. This paper outlines this journey undertaken by the mine planning team, key learnings from implementation and further work required to increase the level of planning maturity. Olympic Dam (OD) is a highly variable, polymetallic orebody with a vertically integrated value chain from operations to final product. The processing plant has a tight set of quality constraints which are managed through timing of stopes from varying parts of the orebody. Value is eroded for the operation when forecasted quality of the mine feed encounters disruptions from unplanned changes to the timing of stope starts. As production has moved from the historic Northern Mining Area into the more geologically complex Southern Mining Area, average stope size has reduced, resulting in increased mining fronts required to meet production targets. This has created a problem of increased schedule complexity and difficulties in identifying and communicating resource priorities within a large set of individual stope critical paths. The problem was approached by considering each stope as an individual project constructed by teams working across multiple projects at any one time. The operation could then be considered a multi-project environment with shared resources and enables the application of Critical Chain Project Management (CCPM) to the mine plan. Key to CCPM is the addition of time buffers to protect the critical path of a project form upstream or downstream processes. Implementation of time buffers protects the stope start date against compliance to plan variance. The monitoring of each time buffer consumption, as a proportion of total construction activities completed enables proactive prioritisation of resources. This resulted in an increase in the number of stopes starting in accordance with the mine plan, simplified communication of priorities to all levels of the operation, increased compliance to plan and a clear measure of schedule risk during planning routines.
Contributor(s):
J Light, L Alford, G Capes and T Woodroffe
-
The application of critical chain project management to sublevel open stoping at Olympic DamPDFThis product is exclusive to Digital library subscription
-
The application of critical chain project management to sublevel open stoping at Olympic DamPDFNormal price $22.00Member price from $0.00
Fees above are GST inclusive
PD Hours
Approved activity
- Published: 2023
- Pages: 10
- PDF Size: 0.596 Mb.
- Unique ID: P-03001-L5X1S6