Drilling Six Ventilation Shafts for the Porgera Goldmine

Difficult ground conditions in the area planned for placement of vent rises to the surface at the Porgera Goldmine led engineers directing the project to chose blind shaft boring methods of shaft construction from the available alternatives. Zeni Drilling Pty Ltd was first contracted in 1988 to install a group of three closely-spaced, steel lined shafts. The success of these led to an order for a fourth hole in the same group followed by two more, less than a kilometre. away, under a separate contract in 1992.
All of the shafts were completed on.schedule to within one day. The only significant difficulty arose during commencement of the last shaft when the strata collapsed trapping the drilling tools and jeopardising the stability of the surface collar pad. The situation was corrected by innovative lining techniques and the project went on to finish on schedule. This paper discusses the application of various technologies associated with the project including aspects of geotechnical input, drilling fluid chemistry, mining engineering and logistics.
Return to parent product
  • Drilling Six Ventilation Shafts for the Porgera Goldmine
    PDF
    This product is exclusive to Digital library subscription
  • Drilling Six Ventilation Shafts for the Porgera Goldmine
    PDF
    Normal price $22.00
    Member price from $0.00
    Add to cart

    Fees above are GST inclusive

PD Hours
Approved activity
  • Published: 1993
  • PDF Size: 0.495 Mb.
  • Unique ID: P199306012

Our site uses cookies

We use these to improve your browser experience. By continuing to use the website you agree to the use of cookies.