Conference Proceedings
Water in Mining 2009
Conference Proceedings
Water in Mining 2009
Pit Water Management in a Mine Planning Cycle, Olympic Dam Case Study
Mine water management is often an afterthought in mine planning processes and can introduce significant risks to projects when studied as a stand alone component at a later stage in the mine design. Incorporation of a mine dewatering and pore pressure dissipation strategy in the early stages of mine planning is imperative in order to minimise constraints on the production schedule, to match designed pit slopes and maximise project value for an open cut mine option such as Olympic Dam. A risk-based mine planning approach was adopted during the project selection phase study whereby water management was introduced into mine planning, scheduling and the development of an operational strategy. Hydrological and hydrogeological studies and outputs were successfully integrated into the various iterations of the mine planning cycle during early selection phase to manage the potential water management risks associated with pit slope depressurisation and access to dry working conditions during rapid advancement of mining phases.An extensive network of vibrating wire piezometer sets and long-term depressurisation testing characterised aquifer conditions and demonstrated that hydraulic connectivity exists within the geological profile due to the presence of structures and resource drill holes which enhance vertical connectivity. This connectivity, along with underdrainage from mining activities contributes up to 100 m of depressurisation in low permeability units.A pit dewatering strategy incorporates the mine planning schedules and accounts for operational constraints as to the location and development of the dewatering wells, storages and pipelines. Numerical modelling generated a range of likely pit inflows and dewatering requirements with the average initial dewatering discharge likely to be 150 L/s and reduce quickly to 50 L/s after five years, depending on the premine schedule.Coupled hydrogeological and geotechnical assessments were also carried out as part of the mine planning cycle and indicate that successful dewatering will go a long way to reduce the pore pressures within key geotechnical units during the rapid mining phase where around 300 m of cover sequence is stripped in five years. However, the residual storage in the primary aquifer and the residual pore pressure in underlying low permeability units will need to be dissipated (in-pit horizontal holes) as the pit floor advances. Pit slope design angles are sensitive to depressurisation and dewatering and up to 70 per cent depressurisation of key geotechnical rock units are required. Whilst an accelerated program of aquifer dewatering supported by lithostatic unloading should drive rapid depressurisation in the lower permeability units, intervention is anticipated in key geotechnical units such as the Tregolana Shale and volcaniclastics. The extent of induced drainage will ultimately depend in part upon the mining rate and geotechnical stability requirements._x000D_
Practical operability testing addressed the potential for operational constraints to mine depressurisation activities such as congestion and mining schedule development within the pit and identified that depressurisation drilling can be achieved even with reduced access availability._x000D_
Mine operations and planning groups established design criteria and considered the likely inoperable periods following rainfall events of seven to 14 days to manage the base surge and minimise impact on production. In-pit surface water management options to minimise operational disruptions during and after significant rainfall events were estimated used a stochastic approach._x000D_
FORMAL CITATION:Douglas, B, Mercer, S, Wright, S and Barclay, D, 2009. Pit water management in a mine planning cycle, Olympic Dam case study, in Proceedings Water in Mining 2009, pp 211-226 (The Australasian Institute of Mining and Metallurgy: Melbourne).
Practical operability testing addressed the potential for operational constraints to mine depressurisation activities such as congestion and mining schedule development within the pit and identified that depressurisation drilling can be achieved even with reduced access availability._x000D_
Mine operations and planning groups established design criteria and considered the likely inoperable periods following rainfall events of seven to 14 days to manage the base surge and minimise impact on production. In-pit surface water management options to minimise operational disruptions during and after significant rainfall events were estimated used a stochastic approach._x000D_
FORMAL CITATION:Douglas, B, Mercer, S, Wright, S and Barclay, D, 2009. Pit water management in a mine planning cycle, Olympic Dam case study, in Proceedings Water in Mining 2009, pp 211-226 (The Australasian Institute of Mining and Metallurgy: Melbourne).
Contributor(s):
B Douglas, S Mercer, S Wright, D Barclay
-
Pit Water Management in a Mine Planning Cycle, Olympic Dam Case StudyPDFThis product is exclusive to Digital library subscription
-
Pit Water Management in a Mine Planning Cycle, Olympic Dam Case StudyPDFNormal price $22.00Member price from $0.00
Fees above are GST inclusive
PD Hours
Approved activity
- Published: 2009
- PDF Size: 4.136 Mb.
- Unique ID: P200910024